Tanker
115,000 DWT
Period :
14 days
Place :
Korea
Completion :
2022.06.22
Vessel Details
Year of Built 2022 Class ABS Flag Marshall IS
Specification for Scrubber
Main Engine
  • CR : 13,000 kW
  • Design load for Scrubber : 85% (11,050 kW)
  • Gas flow at design load : 79,920 kg/h
Auxiliary Engine
  • CR : 1,100 kW
  • Design load for Scrubber : 85% (935 kW)
  • Gas flow at design load : 7,030 kg/h
Boiler
  • esign load for Scrubber : N/A
  • Gas flow at design load : N/A
Scrubber
  • onnection to Scrubber tower : M/E + 3 set A/E
  • Operating condition for design : M/E + 2 set A/E
  • Total Gas : 93,980 kg/h
Time Table
Vessel berthed at Hanla IMS shipyard (Gwangyang)
  • 08 June 2022
Work Start
  • 08 June 2022
Work Complete (Including seatrial)
  • 22 June 2022