Tanker
115,000 DWT
Period :
14 days
Place :
Korea
Completion :
2022.01.22
Vessel Details
Year of Built 2022 Class DNV Flag Liberia
Specification for Scrubber
Main Engine
  • CR : 13,000 kW
  • Design load for Scrubber : 85% (90,720 kW)
  • Gas flow at design load :79,920 kg/h
Auxiliary Engine
  • CR : 1,180 kW
  • Design load for Scrubber : 85% (1,003 kW)
  • Gas flow at design load : 7,030 kg/h
Boiler
  • esign load for Scrubber : N/A
  • Gas flow at design load : N/A
Scrubber
  • onnection to Scrubber tower : M/E + 3 set A/E
  • Operating condition for design : M/E + 2 set A/E
  • Total Gas : 93,980 kg/h
Time Table
Vessel berthed at Sungdong shipyard (Tongyeong)
  • 07 January 2022
Work Start
  • 07 January 2022
Work Complete (Including seatrial)
  • 21 January 2022