300,000 DWT (General Cargo)
Period :
11 Days
Place :
Korea
Completion :
2022.12.12
Vessel Details
Year of Built 2011 Class KR Flag Marshall Is [MH]
Specification for Scrubber
Main Engine
  • CR : 15,820 kW
  • Design load for Scrubber : 60% (9,492 kW)
  • Gas flow at design load : 76,167 kg/h
Auxiliary Engine
  • CR : 1,060 kW
  • Design load for Scrubber : 75% (795 kW)
  • Gas flow at design load : 7,394 kg/h
Boiler
  • esign load for Scrubber : N/A
  • Gas flow at design load : N/A
Scrubber
  • onnection to Scrubber tower : M/E + 3 set A/E
  • Operating condition for design : M/E + 2 set A/E
  • Total Gas : 90,955 kg/h
Time Table
Vessel berthed at Samkang S&C shipyard (Gosung)
  • 1 Dec 2022
Work Start
  • 1 Dec 2022
Work Complete (Including seatrial)
  • 12 Dec 2022