Container
1,800 TEU
Period :
14 days
Place :
Korea
Completion :
2022.01.07
Vessel Details
Year of Built 2016 Class KR Flag KR
Specification for Scrubber
Main Engine
  • CR : 10,500kW
  • Design load for Scrubber : 90% (9,450kW)
  • Gas flow at design load : 79,250kg/h
Auxiliary Engine
  • CR : 1,760kW
  • Design load for Scrubber : 85% (1,584kW)
  • Gas flow at design load : 12,225kg/h
Boiler
  • esign load for Scrubber : N/A
  • Gas flow at design load : N/A
Scrubber
  • onnection to Scrubber tower : M/E + 3 set A/E
  • Operating condition for design : M/E + 2 set A/E
  • Total Gas : 103,700kg/h
Time Table
Vessel berthed at Hanjin Shipyard (Busan)
  • 25th December 2021
Work Start
  • 25th December 2021
Work Complete (Including seatrial)
  • 7th January 2022